As of 1 January 2021, all construction projects undertaken in Poland have to
comply with new energy performance standards for buildings, known as “Standard
WT 2021”. Standard WT 2021 toughens up the requirements in this respect. The new
rules are laid down in §328 and §329 of the “Regulation of the Infrastructure Minister
of 12 April 2002 on technical conditions for buildings and their location” (Journal of
Laws 2019, item 1065) (henceforth the Regulation).

To ensure that new buildings constructed in Poland after 2020 are more energy
efficient, Standard WT 2021 does two main things:

  • lowers the maximum allowed annual demand for primary energy from non-renewable
    sources used for heating, hot water supply, cooling, and ventilation;
  • mandates compliance with certain thermal insulation standards, by setting maximum
    allowed heat-transfer coefficients for interior partitions (i.e. walls, roofs, floors, ceilings)
    and technical systems.

Under §328 of the Regulation, a building and its heating, ventilation, cooling, and hot water
systems – and in the case of public buildings, apartment buildings, production buildings,
commercial buildings and warehouses, also recessed lighting systems – should be designed
and constructed in a way that ensures that the following minimum requirements are fulfilled:

1. the annual demand for primary energy from non-renewable sources, expressed in kWh/
m2 per year, is equal to, or lower than, the maximum value calculated according to the
formula referred to in § 329, item 1 or 3 of the Regulation;

2. interior partitions and technical systems meet at least the thermal insulation requirements
set in Annex 2 to the Regulation.

Standard WT 2021 thus introduces strict regulatory oversight of the heat-loss performance
and annual demand for primary energy from non-renewable sources of buildings
designed from 1 January 2021 onwards, with the aim of minimising energy consumption
and loss as much as possible.

Standard WT 2021 as an element of EU environmental policy

The requirements laid down in Standard WT 2021 are not new to construction
market participants in Poland: they became part of the country’s legal system
already back in January 2014, following the transposition into Polish law of Directive
2010/31/EU of the European Parliament and of the Council of 19 May 2010 on
the energy performance of buildings (henceforth the Directive). Poland decided
to implement the Directive’s requirements gradually, in three steps, known as WT
2014, WT 2017 and WT 2021, so as to make it easier for market participants to
comply.

The aim of the Directive is to significantly increase the number of what it calls “nearly
zero-energy buildings”, thus contributing to the EU’s carbon-emissions reduction
and climate-change mitigation objectives. It defines a near-zero energy building as
“a building that has a very high energy performance, as determined in accordance with
Annex I. The nearly zero or very low amount of energy required should be covered to a very
significant extent by energy from renewable sources, including energy from renewable
sources produced on-site or nearby.”
The need for Member States to make their building stock more energy efficient by
increasing the number of nearly zero-energy buildings was further underscored in
another directive, Directive 2018/844 of the European Parliament and of the Council
of 30 May 2019 amending Directive 2010/31/EU on the energy performance of
buildings and Directive 2012/27/EU on energy efficiency. It orders each Member
State to establish a long-term renovation strategy to support the renovation of the
national stock of residential and non-residential buildings, both public and private,
into a highly energy efficient and decarbonized building stock by 2050, facilitating
the cost-effective transformation of existing buildings into nearly zero-energy
buildings. Recital (8) of its preamble (Official Journal of the European Union L 156,
p. 75) states: “To achieve a highly energy efficient and decarbonised building stock and
to ensure that the long-term renovation strategies deliver the necessary progress towards
the transformation of existing buildings into nearly zero-energy buildings, in particular
by an increase in deep renovations, Member States should provide clear guidelines and
outline measurable, targeted actions as well as promote equal access to financing,
including for the worst performing segments of the national building stock, while taking
into consideration affordability.”

New clause addresses Covid hold-ups in permits

In the final weeks of 2020, as the date of Standard WT 2021’s coming into force drew
nearer, construction industry representatives began to voice concerns about the
situation of projects originated and designed under Standard WT 2017 – i.e., the
rules in force until the end of 2020 – but for which building permits were unlikely
to be issued before 1 January 2021 due to significant delays in the processing of
applications caused by the pandemic. They were worried their projects would
come under the ambit of Standard WT 2021.
Responding to these concerns, the Minister of Development, Labour and Technology
amended the Regulation by inserting a new clause, § 329a, which states that the energy
performance of buildings requirements in force from 1 January 2017 till 30 December
2020 (i.e., Standard WT 2017) apply to construction undertakings with respect to which
at least one of the following was filed, or issued, during that period:
3. application for building permit, for approval of building design, for approval of site/
plot development plan, for approval of architectural design, for building permit
alteration, for approval to resume construction, for approval of replacement
building design, replacement site/plot development plan or replacement
architectural design; or
4. notice of construction (where a building permit is not required); or
5. building permit, approval of building design, approval of site/plot development
plan, approval of architectural design.